South Africa: An Analysis of Country Energy Grids

The grid was not designed for distributed, variable generation. Wind and solar resources are concentrated in the Western, Northern and Eastern Cape, far from demand centres and existing transmission capacity.

South Africa runs on a single interconnected national grid, built around centralised coal-fired power stations in Mpumalanga. The system has three layers: generation, transmission, and distribution. Until recently, Eskom controlled all three.

Table 1: Structure of South Africa’s national electricity grid, 2025

Layer Responsible entity Key facts
Transmission NTCSA (Eskom subsidiary) 33,000 km lines; 170 substations; 575 transformers
Generation Eskom + IPPs Coal dominant; growing wind, solar, gas peakers
Distribution 257 municipalities + Eskom 40% municipal; 60% direct Eskom supply
Regulation NERSA Licences, tariffs, grid code; ERA reform underway
System operator NTCSA (transitioning to TSO) Dispatch, balancing, load management

Sources: NTCSA Transmission Development Plan 2025-2034; NERSA; Meridian Economics, 2024.

The NTCSA, which became a legally separate Eskom subsidiary on 1 July 2024, owns and operates approximately 33,000 kilometres of high-voltage lines, 170 substations and 575 large transformers. Its Transmission Development Plan 2025-2034 calls for 14,500 km of new lines, 210 additional transformers and R112 billion in capital over five years, to accommodate 56 GW of new generation capacity by 2034. Sixty-one projects are in the execution phase, expected to unlock around 30 GW of connection capacity by 2030.

Eskom supplies roughly 60% of end consumers directly; 257 municipalities distribute the remaining 40%. Municipal distributors are hampered by ageing infrastructure, mounting debt to Eskom, cable theft, and governance failures. In Johannesburg, between late March and late April 2024, residents experienced more outages from distribution network failures than they had during equivalent periods of national load shedding. A November 2024 Meridian Economics report described the municipal electricity distribution sector as facing a looming systemic crisis.

Load shedding has been largely absent since May 2025, but outages have not stopped. The Wetility 2025 Energy Resilience Report, based on telemetry from 57 municipalities across all nine provinces, recorded 91,934 unique grid outages in 2025. Households averaged 6 to 9 per month. February was worst: 8.8 outages and 131.8 hours without power per household on average. The problem has moved from the national grid to the distribution last mile.

The grid was not designed for distributed, variable generation. Wind and solar resources are concentrated in the Western, Northern and Eastern Cape, far from demand centres and existing transmission capacity. This geographic mismatch is the single biggest constraint on new renewable connections, according to the NTCSA. The backlog of IPP projects waiting for grid access is growing, and the NTCSA’s plan to unlock 37 GW of new capacity by 2033 through 47 priority projects depends on construction timelines that have historically slipped.

The grid is regulated by NERSA, which issues licences, sets transmission tariffs and enforces the grid code. The Electricity Regulation Amendment Act (2024) provides the framework for a competitive electricity market, including a future independent Transmission System Operator that will manage dispatch separately from the company that owns the physical infrastructure. The timetable for completing that separation remains uncertain.

Cybersecurity is underserved. Kaspersky detected around 300 ransomware attempts targeting South African systems in a single week in February 2023, and the INTERPOL African Cyberthreat Assessment Report (2024) identified the grid as specifically exposed. As embedded solar, smart meters and decentralised generation multiply, the attack surface grows. Neither Eskom nor NERSA has published a public-facing grid cybersecurity strategy.

Eskom projects that generation capacity must grow from 66 GW in 2024 to 107 GW by 2034, driven by population growth, transport electrification and rising industrial demand. The NTCSA’s R112 billion plan is calibrated to support that growth, but delivery depends on procurement processes and approvals that have caused delays before.

The grid’s architecture is not the problem. The reforms separating transmission from generation and opening the market to IPPs are the right moves. What is failing is execution: municipalities that cannot maintain distribution infrastructure, a transmission programme outpaced by connection demand, and no credible cybersecurity posture for an increasingly complex system. South Africa has solved the generation crisis. The grid delivery crisis is next.

This Post was submitted by Climate Scorecard South Africa Country Manager, Jone Carter.

Learn More Resourced

  1. NTCSA. Transmission Development Plan 2025-2034. National Transmission Company South Africa, November 2024.
  2. Meridian Economics. In the shadow of load shedding: An overview of the municipal electricity distribution crisis, November 2024.
  3. Wetility. 2025 Energy Resilience Report: Grid outage telemetry across 57 South African municipalities, March 2026.
  4. ESI-Africa. Cyber threats target energy grid in Africa, July 2025.